AIGNER

Retail, Fashion and Accessories

MAY-OCT, 2018 | BAHRAIN CITY CENTER MALL! HAVELOCK ONE W.L.L

Executed in the time period of 60 Days time with the total construction area of 225m2, this project represents our quality in execution.

We got this project for all Civil related work , this project was challenge because of confined space and coordination between different contractors and joinery supplier as MEP works was awarded to other contractor so we took this project to show our leadership quality and coordinated our works with MEP works so that project can be completed and executed within timeline .

One more major challenge was execution of shop front area as there was big marble slab which has to be installed in ceiling so we made proper MS structure for that and installed the marble with great finishing .

Cubic Interiors