H & M PROJECT

Retail, Fashion and Accessories

OCT, 2014-JAN, 2015 | BAHRAIN CITY CENTER MALL! HAVELOCK ONE W.L.L

Executed in time period of 4 months with total construction area of 3200m2 this project is reflection of our dedication for our work. With total construction area of 3200m2 and project timeline of only 105 days we worked tirelessly to complete the project as per client’s requirement.

We got this project for all works related to gypsum, civil, joinery with condition that we have to complete this project within 105days from date of mobilization to site, we accepted the challenge and started our work. There were lots of challenges while executing the project like limited work hours, all approvals from mall management, limitation in logistics of material. We as company overcome all the challenges to deliver the project within our project time line and cost.

Cubic Interiors